CHAPTER I
INTRODUCTION

This chapter will explain about the background of the research, problem identification, the research objectives, benefit of this research, scope of research, and report writing process phase.

1.1	Background
Recently, Supply Chain management in many companies has rapidly growth. They developed their Supply Chain System to reach efficiency and effective system that will give profit in process and production activity. Inventory, transportation, and information as the key drivers of Supply chain performance. Supply Chain strategy decides what the chain’s configuration will be, how resources will be allocated, and what processes each stage will perform. Strategic decision made by company include the location and capacities of production and warehousing facilities. Inventory is one supply chain performance driver which need to be managed in good system. Important role that inventory plays in the supply chain is to increase the amount demand that can be satisfied by having product ready and available when the customer wants it. Inventory is a major source of cost in Supply Chain and it has a huge impact responsiveness. MRP is one example system that manage inventory effectively inventory and well-known in many company. So this research will observe about material management which related to inventory and MRP system.

1.2	Problem Identification
Decrease generic item purchase order in MRP terminology, that low control in procurement process.


1.3	Research objectives
Objective of the research are:
•	Identify consumption trend of generic item.
•	Analyze the main cause of generic item problem.
•	Evaluate the Existing Outline agreement.
•	Suggestions for generic item management system control.

1.4	Benefit and advantages of research.
Benefit and advantages of research that might be achieved are :
•	Decrease procurement department (MAT) workload.
•	Improvement of  generic system control system.

1.5	Scope of research and the assumption
The scope of research are :
•	Research will be held in Supply  Chain division of TOTAL E&P Indonesie.
•	Observing material management system.
The asumption of research are :
•	Supply Chain System in  normal condition

1.6	Report writing process phase
There are some phases in this report writing, consists of:
BAB I	: INTRODUCTION
This chapter will explain about the background of the research, problem identification, the research objectives, benefit of this research, scope of research, and report writing process phase.
BAB II	 : COMPANY PROFILE
This chapter is explaining about brief description of the company. Profile of the company that being observed.
BAB III   : LITERATURE REVIEW
This chapter is consisting of the theorems that support the observed condition of the research.  This theorems will be based-view of  the data processing.
BAB V    : DATA COLLECTING AND PROCESSING
This chapter describe about data that support the research to analyze the problem, and give recommendation for improvement.
BAB VI   : ANALYSIS AND DATA INTEPRETATION
This chapter will be explain the data analysis, and whether the processing data that related to the problem
BAB VII : CONCLUSION AND RECOMMENDATION
This chapter is explaining the conclusion of the analysis and the recommendations to improve the problem.
REFERENCE
APPENDIX
 
CHAPTER II
COMPANY PROFILE

	This chapter is explaining about brief description of the company. Profile of the company that being observed. Company history, Vision, mission and organization chart

2.1	Company history
TOTAL E & P INDONESIE, a 100% Indonesian subsidiary of the Paris based TOTAL Group, was incorporated in Jakarta on 14 August 1968. Since then it has been working in partnership with the Indonesian Government, as a Production Sharing Contractor in the search for, and development of, Indonesia’s vast hydrocarbon reserves. Early work involved geological studies and seismic acquisition. Exploratory drilling started in the inhospitable swamps of Jambi in South-East Sumatra. But it was in East Kalimantan, on the Mahakam Contract Area, that TOTAL E&P INDONESIE, as operator for their association with INPEX since 1970, found success. 
TOTAL E&P INDONESIE’s activities during more than three decades can be summarized in two major phases. 
•	A first phase concentrated on oil production and started with the discovery of the Bekapai and Handil oil fields respectively in 1972 and 1974 in the Mahakam Contract Area. These fields started to produce in 1974 and 1975 respectively, oil production reached its peak in 1977 with an average of 230 000 bopd and today continues to gradually decline. Enhanced recovery programs have been carefully studied and implemented to slow the decline and optimize the overall hydrocarbon recovery. 
•	In the second phase, TOTAL E&P INDONESIE oriented its efforts on the hydrocarbon potential of Mahakam towards natural gas as the key to its future in East Kalimantan. Exploration and appraisal works led to discoveries of considerable reserves of gas in Tambora, Tunu, Sisi, Nubi, and PEciko fields. 

 
Figure 1.1 Areas of Oil-and-Gas-Production Fields

As gas production and processing units from these fields have been progressively brought on stream, TOTAL E&P INDONESIE has become the largest gas producer in Indonesia supplying over 60% feed gas Bontang Plant, the largest producing LNG plant in the world. Feed gas also supplies the East Kalimantan industrial zone where fertilizer, urea, methanol, and ammonia plants are located to supply the domestic market. 
The current hydrocarbon output from the Mahakam Block is on average approximately equivalent to 500 000 barrels of oil equivalent per day (boepd) (or 80 000 bopd of liquid hydrocarbon and 2 400 Million standard cubic feet or gas per day (MMscfd). On March 21, 2004, TOTAL R&P INDONESIE reached its highest ever daily production of 584 927 boe including 2 725 MMscf gas. 
In the coming years, TOTAL E&P INDONESIE will continue to develop the Mahakam fields with the aim of increasing hydrocarbon production and sales.

2.2	Areas and Production Fields
The areas of  TOTAL E&P INDONESIE production fields are: 
2.2.1	Bekapai 
		Discovered in 1972, Bekapai is a complex oil field covering an area of 20 square kilometers in the Makassar Straits off the coast of East Kalimantan. At present, the average production is around 2 500 bopd.

 
Figure 2.2  Bekapai oil Field 
2.2.2	Handil 
		This oil field was discovered in 1974 located at the edge of the Mahakam River Delta among swampy islands which are partially submerged at high tide and covered by thick layers of local vegetation known as Nipah-Nipah. Current production is around 13 000 bopd. 

 
Figure 2.3 Handil Field
2.2.3	Tambora and Tunu 
Located in the central part of the Mahakam delta lies the Tambora field an oil and gas field. Tunu is a giant gas and condensate field covering 400 square kilometers stretching 80 km from North to South in shallow water along the coastline on the outer limits of the Mahakam River Delta. Production of Tambora and Tunu fields started in 1989 and 1990 respectively. 
    
Figure 2.4 Tambora and Tunu Gas Field 

2.2.4	Peciko
	This gas field was first discovered in 1983, 60 kilometers offshore, north –east of the city of Balikpapan and south-west of Bekapai in the Makassar Straits. Production at its initial level of 400 MMscfd is increasing gradually about 1 300 MMscfd of gas by 2004 with the development of additional platforms, the drilling of new wells and the installation of onshore process and compression facilities. 
 
		Figure 2.5 Peciko Gas Field 

2.2.5	 Senipah Oil and Condensate Handling Terminal 
		In response to the increasing production at Handil and the adverse conditions on site, a permanent terminal was built near the village of Senipah some 20 kilometers south of Handil. 

 
Figure 2.6 Senipah Oil Gas 

	Completed on 1976, the Senipah Terminal which received crude oil from Handil and Bekapai, now also receives condensate from Tambora and Tunu and gas for processing and compression from Peciko. Since 1982 the Handil and Bekapai associated gas has been sent to the Bontang LNG Plant. The processed crude and condensate are stored and exported separately 

2.26	Bontang LNG Plant 
		TOTAL E&P INDONESIE became a 10% shareholder of PT Badak NGL Co. Ltd. in 1993.

 
Figure 2.7 Bontang LNG Plant

2.3	Supply Chain Division policy
Total E&P Indonesia shall ensure that all contractual relationships for supply of goods and services in support of Total E&P operations must be committed in accordance with the Company procedures. The Supply Chain Division (SC) is the owner of the company’s EKD supply chain business process, and it exists in order to maintain and administer the company supply chain policies and procedures.
•	Supply Chain are responsible for complying with all policies, rules and regulations imposed on the supply chain processes, specifically those from the Total group and from BP MIGAS. In addition the general commitment to Health, Safety, the Environment, Code of Conduct and Sustainable Development shall be observed at all times. 
Supply Chain mission :
•	The SC mission is to provide Goods and Services at optimal cost, in order to achieve effective, efficient operations and customer satisfaction.
The following overriding principles shall be observed by all personnel involved in any activities related to the TI supply chain process
• 	Competition: Competition is to be encouraged as far as possible. Any direct award must be justified and conducted with the rigour required to maintain competitiveness of the services being provided.
• 	Transparency: All activities performed in the supply process must be clearly justified by adequate documentary evidence and able to be audited.
• 	Independence: Where ever possible, the commercial and technical aspects of a tender should be handled separately.
• 	Objectivity:  The criteria used in selecting suppliers must remain objective at all times, be consistent with the goals / purpose in hand and be measurable.
• 	Confidentiality: Access to and disclosure of confidential information contained in tender enquiries and subsequent Contract must be strictly limited & controlled.
• 	Fairness: 	Suppliers must at all times be afforded equal opportunity and be treated in the same manner, especially during a tendering process.
2.4	Supply Chain and Coordination Objective
Supply Chain Key Objectives are :
•	Responsible for complying with all policies, rules and regulations imposed on the supply chain processes, specifically those from the Total SA group and BP MIGAS,. In addition the general commitment to Health, Safety, the Environment, Code of Conduct, Business Ethics and Sustainable Development shall be observed at all times during all supply chain activities.
•	Monitor the functioning of the material and services procurement chain as well as the warehousing to ensure the material and services needs of the Company are properly taken care of in a cost efficient manner
•	Manage and develop human resources for the Division
•	Provide link through Jakarta coordination team (DC) between PSC supervisory authorities or partners and user-Divisions in the District
•	Develop relationship with local authorities and act as a correspondent on all procurement regulatory matters in the District
•	Ensure the Company’s inventory are properly controlled, maintained and safeguarded
•	Control and improve the suppliers/ contractors quality database through Supplier Relationship Management.
•	Ensure proper coordination within other Divisions in DK and provide required information to other relevant parties
•	Ensure compliance with HSE requirements, SOX, and other Group requirements.
•	Prepare and manage divisional budget and control cost

 
2.5	Organizational chart
2.5.1	TOTAL E&P INDONESIE Organizational chart
TOTAL E&P INDONESIE, organizational chart is shown below:

Figure. 2.8
TOTAL E&P INDONESIE ORGANIZATIONAL CHART 
2.5.2	Supply chain Division organizational chart 
Supply Chain (SC) Division, organizational chart is shown below: 
 
Figure. 2.9
Supply Chain Division  ORGANIZATIONAL CHART 
CHAPTER III
LITERATURE REVIEW

In this part there are related theories about the research subject that become the based-view of the data processing and support the research.

3.1	Supply Chain management
A Supply Chain consists of all parties involved, directly or indirectly, in fulfilling a customer request.. The supply chain not only includes the manufacturer and suppliers, but also transporters, warehouses, retailers, and customer themselves. Within each organization, such as manufacturer, the supply chain includes all functions involved in receiving and filling a costumer request. These functions include, but are not limited to new product development, marketing, operations, distribution, finance, and customer service. 
 
Figure. 3.1
Supply Chain activities

Supply Chain activities begin with a costumer order and end when a satisfied customer has paid for his purchase. The primary purpose for the existence of any Supply Chain is to satisfy customer needs. The supply/value chain of an organization is the entire chain or network of organizations, technologies, and capabilities that together deliver goods or services to the customer.  It is generally the essence of the organization’s existence and creation of wealth, and is usually its most critical business process
 
Figure. 3.2
Value chain of Supply Chain activities

The term supply chain conjures up images of product or supply moving from supplier to manufacturers to distributors to retailers to costumer along a chain. But most supply chains are actually networks.  A typical supply chain may involve a variety of stages. These supply chain stages include :
•	Customers
•	Retailers
•	Wholesalers/Distributors
•	Manufacturers
•	Logistic/transportations
•	Component/ raw material supplier
 
Figure. 3.3
Supply Chain (Hub system)

3.2	Supply Chain performance drivers.
Company achieves the balance between responsiveness and efficiency in its supply chain that best meets the needs of company’s competitive strategy. To understand how a company can improve supply chain performance, by examine the factors drivers of Supply Chain performance. These factor drivers also determine whether strategic fit is achieve across the supply chain. Supply Chain performances drivers include:
•	Facilities are the places in the supply chain network where product is stored, assembled, or fabricated. The two major types of production sites and stores sites .Whatever the function of the facility, decisions regarding location, capacity, and flexibility of facilities have a significant impact of the supply chain’s performance. For instance, a highly-efficiency distributor would have fewer warehouses to increase efficiency despite the fact that this practice will reduce responsiveness.
•	Inventory is all raw materials, work in process, and finished goods within a supply chain. Inventory is an important supply chain because changing inventory policies can dramatically alter the supply chain’s efficiency and responsiveness.
•	Transportation entails moving inventory from point to point in the supply chain. Transportation can take the form of combination of modes and routes, each with its own performance characteristics. Transportation choices have a large impact on supply chain responsiveness and efficiency. 
•	Information consists of data and analysis concerning facilities, inventory, transportation and customers throughout the supply chain. Information is potentially the biggest driver of performance in the supply chain as it directly  affects each of the other drivers. 
 
Figure. 34
Supply Chain performance driver


3.3	Inventory planning in Supply Chain.
Inventory exists in the supply chain because of a mismatch between supply and demand. This mismatch is intentional at steel manufacturer where it is economical manufacturer in large lots that are then stored for future sales. The mismatch is also intentional at a retail store where inventory is held in anticipation of future demand. An important role that inventory plays in the supply chain is to increase the amount demand that can be satisfied by having product ready and available when the customer wants it. Another significant role inventory plays is to reduce cost by exploiting economies of scale that may exist during both production and distribution. Components of inventory decisions that supply chain managers must make effectively create more responsive and more efficient supply chain are :
•	Cycle inventory is the average amount of inventory used to satisfy demand between receipt of supplier shipments. The size of the cycle inventory is a result of the production or purchase of material in large lots. Companies produce and purchase in large lots to exploit economies of scale in the production, transportation or purchasing process. With the increase in lot size, however also come increases in carrying costs.
•	Safety inventory is inventory held in case demand exceeds expectations; it is held to counter uncertainty. If the world were perfectly predictable, only cycle inventory would be needed. Because demand is uncertain and may exceed expectations. However, companies would safety inventory to satisfy an unexpectedly high demand. Managers face a key decision when determining how much safety inventory to hold. Choosing safety inventory involves making a trade between the costs of losing sales due to not having enough inventory.
•	Seasonal Inventory is inventory that is built to counter predictable variability in demand. Companies using seasonal will build up inventory in a periods of low demand and store it for period of high demand when they will not have the capacity to produce all that is demanded. Managers face key decisions in determine whether to build seasonal inventory. And if they do build it, in deciding how much build. If a company can rapidly change the rate of its production system at very low cost then it may not need seasonal inventory because the production system can adjust to a period of high demand without incurring large costs. Therefore, the basic trades off supply chain managers face in determining how much seasonal inventory to build is the cost of carrying the additional seasonal inventory versus the cost of having a more flexible production rate.
•	Sourcing  is the set of business processes required to purchase goods and services. Mangers must first decide the tasks that will be outsourced and those that will be performed within the firm. For each task, the manager must decide whether to source from single supplier or a portfolio of suppliers. If a portfolio of multiple suppliers to be carried, the role of each supplier in the portfolio must be clarified. The next step is to identify the set of  criterion that will be used to select suppliers and measures the performance. Managers then select suppliers and negotiate contracts with them. Contracts should be structured. To improve supply chain performance and minimize information distortion from one stage to the next. Contracts also clearly define the role of each supply source. Once suppliers and contracts are in place, procurement processes that facilitate the placement and delivery of orders play a major role. Sourcing decisions are crucial for a firm because they affect all other inventory decisions and the level of efficiency and responsiveness the supply chain can achieve.

3.4	Uncertainty in Supply Chain; Safety inventory
Safety inventory is inventory carried for the purpose of satisfying demand that exceeds the amount forecasted for a given period.   Safety inventory is carried because demand forecasts are uncertain a product shortage may result if actual demand exceeds the forecast demand. A supply chain manager must consider when planning safety inventory. On one hand, raising the level of safety inventory increases product availability and thus the margin captured for customer purchases.
The appropriate level of safety inventory is determined by the following these factors :
•	The uncertainty of both demand and supply
•	The desired level of product availability
•	Lead time variability
•	Replenishment lead time

3.5	Material Requirement Planning (MRP) system.
Material Requirement Planning is planning and controlling system of material (parts) which dependent into higher level of material parts. This condition is impact of complementary system in production, for instance when raw material and assembly component is complementary in creating complete product. This dependent condition is random and lumpy. Lumpy demand is random pattern and discontinued demand, where large demand being order in a period or there is no demand at all in other period. 
Material requirement planning objectives is planning material and scheduling for components and sub assembling product. MRP support Mater Production Scheduling (MPS) forecasting future demand of components parts. This demand influence by On hand inventory and Schedule receipts (SR) according to time phase, so production size is able to schedule whenever needed.
 	There are four abilities which are MRP system characteristics:
•	Able to predict demand in the proper time
	MRP able to predict how long is the proper time for job completion or when material should be available to fulfill demand of products which is scheduled in Master Production Scheduling.
•	Composing minimal demand for each item
	By mean of product demand, MRP able to composing accurate scheduling system (priority) in fulfill minimum demand of each item.  
•	Decide Re-order planning in proper condition
	MRP indicate reorder planning of material to fulfill product demand, whether outbound or inbound demand.
•	Able to rescheduling or postponement of planned scheduled.
When production capacity is unable to fulfill product demand, MRP indicate rescheduling planning to define real order priority.  

 
Figure. 3.5
Material requirement Planning flow process
 	Figure 3.5 describe about MRP system which divided into 2 parts:
•	MRP Input 
1.	Master production scheduling
MPS is according to forecast of product demand. Long term forecast support short term forecast which contain detail plan of “production size” and “production period” with considering available resource.
2.	Inventory master file
Inventory master file describe status of level item in inventory. Inventory level of each item has to be identified clearly, transactions that being occurred, receiving, consuming, defect, data about lead time, and production size are the main data to avoid planning mistakes.
3.	Product structure file ( Bill Of Material)
Product structure describe about relationship of each components in assembling process. This information being processed to define the real demand, beside that product structure contain component demand information in every step of assembly process.
•	MRP Output 
Output of MRP system is determined the quantity of each item according to BOM and schedule of each item being needed. This information being processed to create Planned Order Release (POR). Planned order release contain 3 main activity; work orders, purchase orders, and rescheduling. 
 
CHAPTER IV
RESEARCH METHODOLOGY
	
 Research needs a methodology that suitable with the objective. Research methodology describe the all the step process from the problem identification until conclusion. (Figure 4.1)

4.1	Problem Identification.
This process phase is the initial phase of all research process. Observing the real condition of the system and directing the step process to reach the research objectives. In this phase, we have to identify the problem in the real Supply chain system and compare it with the ideal system.

4.2	Literature study
This phase is making some review that relevant with the identified problem. Some theories which related to the problem, there are Supply Chain management, Supply Chain performance drivers, Inventory planning in Supply Chain, Uncertainty in Supply Chain; safety inventory, Material requirement planning system.

4.3	Field study
In this phase, real problems in field are observed. Observing Supply chain flow process, procurement process, material management, and generic item control system. It takes some period to get accurate result of observation. 

4.4	Data Collecting and processing
This phase is continuing phase from the phase before. Data obtained by capturing in the system. Data processing in this phase is clustering by classification and finds the consumption level of each material.

4.5	Data analysis and data interpretation.
This chapter will be explaining the data analysis, and whether the processing data that related to the problem. Analyzed some critical factors, and find the impact of those factors. Data interpretations are describing the data and get the patterns of consumption level. This chapter include initial recommendation for root causes.

4.6	Conclusion and recommendation.
The research last phase are taking conclusion and give some suggestion from the result of the research. Conclusion taking is the answer of the existing problem. Beside that, some suggestion will be given as input in relation with the research.

 

Figure 4.1
Research methodology flow process 
CHAPTER V
DATA COLLECTING AND PROCESSING

Data collecting is taking some material data to support the research and the main data to analyze the system. Before analyzing system, data were processed according to the research objectives.
5.1	Data Collecting
5.1.1	Supply Chain management system in TOTAL E&P Indonesie.
Main objective of Supply Chain management system in TOTAL E&P Indonesia is to provide Goods and Services at optimal cost, in order to achieve effective, efficient operations and customer satisfaction Supply Chain are responsible for complying with all policies, rules and regulations imposed on the supply chain processes, specifically those from the Total group and from BP MIGAS, the regulator for the Indonesian Upstream Oil & Gas Industry.
Supply Chain is only one actor in the supply process and can only contribute as a co-responsible with other actors.  SC organization is committed to attracting and developing personnel to ensure a professional discipline providing the following services;
•	 CTC – Contracting for the Supply Services.
•	 MAT – Procurement of Goods.
•	 STO – Management of TI Inventory stocks.
•	 TAW – Transit, Importation, Acceptance and Warehouse.
•	 MPL – Development of Methods and Supply Chain Improvements.
The contracting, procurement and inventory management activities are executed by so called “Duets”, consisting of representatives of SC and the user departments, in order to ensure a coordinated joint approach to these activities. In line with Government Regulations/Guidelines(PTK 007) which allows for procurement activities below 100K USD to be administered through a procurement committee within Supply Chain. For all East Kalimantan District (EKD) procurement above US$ 100K, the Bid Committee Balikpapan (BCB) administers the procurement activities. To avoid any conflict of interests, the Bid Committee Balikpapan are independent of both the Supply Chain Division and the EKD organization, reporting directly to the Coordination Division. 
All process in the Supply Chain management system is captured by Supply Chain Intranet (Supply Chain Information system). This system called paperless system. This integrated system simplifies the Supply Chain process. The other benefits are minimizing the expenses and shorten the process.

5.1.2	MRP system in TOTAL  E & P Indonesie
Material Requirement Planning (MRP) system in TOTAL E&P Indonesie is used for efficient planning and checking of the stocks and stock replenishments on the basis of replenishments strategies defined and the requisitions recorded in the system. Automatically create procurement proposals for purchasing and production (Planned orders, purchase requisitions, or delivery schedules). These strategies based on the nature of the items and the suppliers.
MRP is a complex process which takes into account existing stock, existing material reservations, planned work, outstanding goods receipts, items under repair and stock levels. SAP R/3 provides functions to calculate how many materials need to be ordered according to these parameters.
 
Figure5.1 MRP system
Offshore reservations. Work orders will automatically create reservations for all of the stock materials which are required. Users can also create reservations manually if there is no work order.
Master Data. Material master data contains information which is vital for MRP. SAP uses several parameters to calculate if a stock level is too low and needs to be replenished.
Stock levels / status. MRP checks on the status of current stock levels including items under repair which may be returned to stock within a number of days. MRP will only work successfully if the stock levels are accurate. This means always creating a goods issue when an item is taken from stock and running a periodic inventory count. 
Having considered the three different inputs MRP produces a report called the MRP list which shows all of the stock items which need to be ordered. For each of the materials it creates a planned order. The MRP controller or material owner checks this list, verifies details if necessary, and the system automatically creates purchase requisitions for the required materials from the planned orders.



5.1.3	Management criteria of MRP system
The management criteria are determined when the tem is created on the basis of the estimated consumption; the procurements lead time and the criticality of the item. They are defined at plant level. The relevant parameters are determined by the Technical Administrator and the Stock controller in charge of referencing. These people set the reorder people (ROP) and determine whether or not planned needs are taken into consideration.

5.1.4	Type of planning in MRP terms
There are three MRP types of planning are as follows:
•	V1 : Consumable items. Planning based on the reorder point by considering needs ( Stock items)
•	PD : Planning and safety/Insurance items. Replenishment according to actual demand and safety stock. (Stock item)
•	ND : Non stock/direct purchase. There is no planning, the item is not processed by the MRP module (Non stock item).

5.1.5	Non stock/Direct purchase material
Non stock/direct purchase material is a type of material which is not processed by MRP module. User who needs the material makes their own purchase order and purchase requisitions. This type must not be used for  stock items. 

5.1.6	Generic item terminology
 Generic item is Non stock/direct purchase material which is not registered on company’s material master and falls into non technical equipment, moveable asset, and one time purchase of specific assembled technical equipment. Generic item should be having low value.  


5.1.7	Material requisition flow for generic item
Material requisition flow describes the flow process of material from material requirements until procurement and people who involve the process. 
 
Figure 5.2
Material requisition flow for generic item

When user needs material at the first time they have to check in material master. If the material that user need is available in  material master, then user have to raise a reservation. In condition when there isn’t any material master and classify as non catalogue material then user have to specify material description, certification required, QA/QC, Engineering Estimate  requirement in the Purchase Requisitions (PR). Prior to PR Approval, cost controller will check the budget allocation. Last, the PR ready to release to procurement process.

5.1.8	Procurement data from Purchase order and contract Release order for generic item.
This data is total number of purchase order (PO) and contract release order (CRO) for generic item between 01/01/2005 and 28/05/2007. In that period company has spent for PO & CRO of generic item for USD 22,036,237.64 or 4.13% of total expense.. The partition of the commitment is shown in below figures.

 
Figure 5.3
Partition of generic item by value

 
Figure 5.4
Partition of generic item by commitment

This chart shows that the biggest consumption level of generic item is in DRL department followed by FO department. Meanwhile in term of item purchased, FO department is leading with 32% of 1404 commitment.

5.1.9	Total of generic item procurement in yearly basis Data.
These charts show data of generic item procurement between 2005 until 2007 in yearly basis. 
 
Figure 5.5
Evolution chart of generic value  by commitment and generic to all

Figure 5.5 defined the evolution chart of generic item in yearly basis. The value of the chart defined the commitment value of generic item in every year and comparison of generic procurement with other planning type procurement. This chart shows the improvement of generic item management. In 2005, the value of generic represent 4.5% of total commitment generated in a year, increased to 5.6% in 2006, and decreased significantly to 1.7 % up to mid 2007.
 
Figure 5.6
Evolution chart of generic commitment by commitment and generic to all
Figure 5.6 defined the evolution chart of generic item in yearly basis. The value of the chart defined number of commitment of generic item in every year and comparison of generic commitment with other planning type procurement. The consumption trend of generic item is decreased. In 2005, the number of commitment is 25.6% of total commitment issued and then decreasing to 14.2% in mid 2007.

5.1.10	Data of generic item by procurement method.
This is the data of procurement method that occurs in generic item procurement between 2005 until 2007. There are four methods in procurement process; Call for tender (CFT), direct Appointment (DA), direct selection (DS) and top ten procurement.

Procurement Method	Value	Nb Commitment	% Compliance to value threshold	Ratio (USD/PO)
CFT	5 Mio	78	100%	63 K
DA	9,8 Mio 	802	72.90%	12 K
DS	 6,5 Mio 	285	87.00%	22 K
TOP 10	 943 K 	4	 	236 K

Table 5.1
Table of generic item by procurement method

The most common procurement method to buy generic item is Direct appointment ( DA) which reach 802 number commitment worth value is 9.8 Million USD.

5.1.11	Direct appointment data in generic item terms.
This is the data of generic item procurement with direct appointment method between 2005 until 2007. Direct Appointment is the procurement goods/service which is conducted by way of direct appointment to 1 (one) supplier of goods that widely known able to supply. DA can be conducted to procure to sole agent or with the value less than 5K. DA may be used for bigger value then 5K when there is a justification. In below table we breakdown the Direct appointment in four transaction value; <5K, <20K, <100K and >100K. This data show the number of commitment in each transaction value. The biggest commitment is for commitment worth less than 5000 USD (5K). We can can get the conclusion that most of the procurement process are in compliance.

Transaction value	Nb of Commitment	Value
 < 5K	648	1,369,555.27
 < 20K	340	3,708,169.85
 < 100K	144	6,732,632.19
 > 100K	37	10,225,880.33

Table 5.2
Table of direct appointment method in generic items procurement
	

5.1.12	Generic item data in material category.
This is the data of generic item procurement by material category in 2005-2007. This data consist of generic item value and generic item commitment by material category. Company has own policy about the consumption level of generic item. 

 
Figure 5.7
Generic item data in material category

Company policy is considering the biggest number of commitment than the value to be observed So from this data we can see the consumption trend of generic item by number of commitment. The big three of number of commitment are machine/hand tools with 278 Nb of commitment, personnel safety equipment with 217 Nb of commitment, and office equipments/parts with 211 Nb of commitment. These category consumption level totally is 703 Nb of commitment ( 60% of total number of commitment). We will observe these material category furthermore.

5.1.13	Active Outline agreement until 2007
Outline agreement is a long term contract to one and several supplier which normally covers recurring requirement, consumables, low value expenditure or material/service under a sole agent. The utilization of OA is recommended to increase efficiency and cut-back administrative task in repetitive tendering process. Using auto-CRO, the commitment process will only take less than 2 working days. Company has 110 Outline Agreement which valid until 2007 .  This data is enclose in appendix (A.1)
5.2	Data processing
Data processing in this research is to find the consumption trend of generic item, by counting and clustering raw data of generic item procurement and into the same material category between 2006 and 2007.

5.2.1	Data of generic item user (departments) in material category
Data of generic item user in material category (figure 5.7) describe the consumption level in material category.  From that figure, we decide to evaluate big 3 generic item consumption level (number of commitment) in material category. These big 3 represent the consumption trend of generic item which are Machine and hand tools, personnel safety equipment, office equipment/parts. These category will be evaluate furthermore

5.2.1.1	Data of generic item user (departments) in machine and hand tool category.
		In 2006-2007 the category of  machine and hand tools is the most frequently purchase in generic item data. This figures data describe consumption level of generic item in each department in TOTAL E&P Indonesie. 
 
Figure 5.8 Machine and Hand tools purchase order

There are two departments who have the highest consumption level of generic item. FO/MNT department with 30 purchase order and then followed by DRL/CWO department with 25 purchase order.
Repetitive material order of machine and hand tool category describes this material occurrences in purchase order that made by FO/MNT and DRL/CWO departments. We can get this data by processing the total of purchase order data in each department .Figure 5.9 shows that there are 5 material that occurs in purchase order more than one times. The materials are Bow turbolizer, injection relay test, digital camera, Industrial video system, and Ultrasonic monitoring system. The most frequently purchase are bow turbolizer and injection relay test by 3 times.

 
Figure 5.9
Repetitive material in machine and hand tools purchase order data

5.2.1.2	Data of generic item user (departments) in personnel safety equipment category.
Personnel safety equipment is in the second place of the most frequently purchase of generic item data. This figures data describe consumption level of generic item in each department in TOTAL E &P Indonesie.

 
Figure 5.10
Personnel safety equipment purchase order

There are two departments who have the highest consumption level of generic item. FO/AMT department with 27 purchase order and then followed by DRL/CWO department with 14 purchase order.
In personnel safety equipment category both FO/AMT and DRL/CWO departments have the highest number of generic item procuring with 41 purchase orders.  So  we analyzed these departments data for the category. The figure shown, the most frequently generic item bought in this category is Antiflame protective clothing with 5 times during this period.
 
Figure 5..11
Repetitive material personnel safety equipment purchase order data
5.2.1.3	Data of generic item user (departments) in office equipment/parts category.
Office equipment parts/category is in the third place of the most frequently purchase of generic item data. This figures data describe consumption level of generic item in each department in TOTAL E & P Indonesie.

 
Figure 5.12
Office Equpment/parts  purchase order

There are two departments who have the highest consumption level of generic item. FO/AMT department with 30 purchase order and then followed by SC/TAW department with 17 purchase order.
In personnel safety equipment category, FO/AMT and DRL/CWO departments have the biggest number of generic item procuring with 41 purchase orders (5.1.2).  We are processed that data to get the repetitive material order. 

 
Figure 5.13
Repetitive material in office equipment/parts purchase order data

This chart shows us the consumption level of material. The most significant number of repetitive material order is office chair with 8 po or 23 % of total repetitive material order in this category.  The other materials, which need to be evaluated, are Plywood, nail and bangkirai wooden.  Three of them have 4 repetitive material order during this period.

5.2.1.4	Active Outline agreement data in Machine and hand tool, personnel safety equipment, office equipment parts/purchase category.
This data shows the active outline agreement which valid until 2007 in above 3 material categories This data is taken from appendix (A1) and processed in SAP. The category of Machine and hand tools has 2 Outline Agreements, Office equipment/parts has 4 outline agreement, and Personnel safety equipment has 8 outline agreements.

 
Table 5.3
Active OA for 3 categories 
CHAPTER VI
 DATA ANALYSIS AND DATA INTEPRETATION

This part described about results analysis of data collecting and data interpretation in this research. The analyses are: 
6.1	Analysis of Generic item problem
Main problem of generic item is high consumption level in this category. Generic item considered as low value purchase and one-time purchase. If the purchasing activity occur more than one times, this should be categorized non generic item.
 Figure 6.1
Fishbone diagram

In the real system, root causes of high consumption levels of generic item are uncovered material in outline agreement, human and repetitive material purchase. In term of value, the problems are considered as simple problem for supply chain, but if they are not managed in a good system this problem will increase procurement department workload and make Supply Chain management system run ineffectively.
First root cause of high consumption level is uncovered material in outline agreement. Company has made Outline agreement (OA) to covered demand of low value material.  For 2005 until 2007 company has 110 outline agreements. But in some cases, the existing outline agreement was not effective. Because not covering user demand. This mistake is impact of bad OA planning and unidentified future/consumption planning. Officers generate OA without communication with user. They should be understood the rule and policy of OA proposal. At least, observe the consumption trend of the material and identified future consumption planning before deciding to make Outline agreement. In the real system company has low control in OA evaluation, whether the existing OA has covering generic item demand or not. But company can decrease these problems by evaluate OA periodically. 
Second root cause is human factor. Some user has bad habit, easier the process system to minimize replenishment process by using generic item terminology.  This point of view is minimize replenishment time of user but increasing the procurement department workload. Material management terminology is not well-known by some user. For instance,  when user ordering some material, user lack of information about how to find material in UNISUP (software for material management). This lack of information makes user buy material in generic item to replenish material.
Third root cause is repetitive material purchase. TOTAL E &P material management system has a policy in manage generic item. Generic item should be purchase in one time in some period, but the reality is for some identical material being bought in generic item terms for many times. For this kind of material, should be not categorized as generic item but other material management category such as direct purchase and include in material master (catalogue). So company can manage and control it. But in some cases, repetitive material purchase is impact of un-userfriendly system in managing material. Users difficult to find the catalogue then decide to make new requirement in generic item terms.  

6.2	Analysis of Generic item management in yearly basis.
 Generally, generic item management is improving from the first time implemented. Generic item management evolution is decreasing in 2005 trough 2007. Figure 5.5 defined the commitment value of generic item every year is decreased and the generic item procurement is increase in 2006 then go down in 2007.  This evolution is significant improvement of generic item management. Meanwhile figure 5.6 shows the number of commitment generic item in every year and comparison of generic procurement with other planning type procurement. The data shown the decreasing trend of commitment in 2005 through mid 2007.  From this data in 2005 number of commitment is about 600 and decreasing to 150 in 2007. Although number of commitment in yearly basis is decreasing, but 150 number of commitment is a big value that still weight the procurement department workload. This number commitment considered as more important than big value of generic item. Big value of generic item could happen for expensive material which is uncatalogue. It’s a common problem, in condition requiring generic item classification. 

6.3	Analysis of generic item by procurement method.
In purchasing generic item, user can use all the procurement method. There are no special criteria to procuring generic item, in condition requiring procurement procedure. In table 5.1 we can see the biggest procurement that being used in procuring generic item is direct Appointment ( DA) with 802 number of commitment. This procurement method is known as the shortest way to minimize procurement time because procurement goods/service which is conducted by way of direct appointment to 1 (one) supplier of goods that widely known able to supply or procure to sole agent or with the classification of value transaction.  But buyer still evaluate vendor related to the rule. From the table 5.2 which is describe about direct appointment transaction value, we can see the biggest commitment is for commitment worth less than 5000 USD (<5K). This value is suitable for generic item which classify as low value material. 

6.4	Analysis of generic item data by material category.
From figure 5.7, we can see the consumption level of generic item in material category. According to the company policy in evaluating generic item, this research considered to the number of commitment which made during 2005 until 2007. Observing number of commitment is more critical than purchasing value of generic item. In material category, machine and hand tools has the biggest number of commitment then followed by personnel safety equipment and office equipment parts. Other category distributed into average commitment number. 
Machine and hand tools category has the biggest number of commitment with 119 purchase order. More than 50 % of total commitment in this category is made by FO/MNT  and DRL/CWO. We can see it in figure 5.8. Machine and hand tools are technical material in production operation and these departments are main core of company production operation. In this category company has 2 outline agreements to cover demand. But the real fact is high demand of machine hand tools were not covered by these OA. These OA is used effectively but not efficient in covering generic item demand, so user preference to buy in generic item terms. So recommendation for this category is when buyer makes outline agreement they have to considering the consumption trend of the material. We can observe the consumption trend by evaluate the repetitive material purchase in this category. We can see it in figure 5.9.  In these departments, there are 5 materials which buy repeatedly and these materials recommended having new Outline Agreement. 
Personnel safety equipment is in the second place the most frequently purchase or big number of commitment with 105 purchase order. The biggest department is FO/AMT then followed by DRL/CWO, we can see it in figure 5.10. Their purchase order take the biggest part of total purchase order in this category about 75%. These department are one of the main core of company work area, in production. These departments need a lot of attention in safety equipment. All the materials that being buy in this category, quite rarely buy or one time purchase materials except two materials, Dale antiflame protective clothing and working jacket.  We can see it in figure 5.11. These materials have 8 times repeatedly purchase in this observed period. This category already has 8 outline agreement to cover demand in this category. From table 5.13 we can see that these Outline Agreement are not used effectively, average usage level is under 100%. And then consumption level in this category is still high, so existing Outline Agreement not covering demand in this category. These existing Outline agreements were not used effectively and not efficient to covering demand. For these cases, we have to evaluate existing OA and decrease the value or extending consumption range period. and then decrease consumption level in this category by make new Outline agreement specially for repetitive material purchase, Dale antiflame protective clothing and working jacket.
Office Equipment/ parts category is in the third place of the most frequently purchase or big number of commitment with 95 purchase order (po). Departments which have the highest level of consumption in this category is FO/AMT department with 30 purchase order and then followed by SC/TAW department with 17 po. This consumption level not really represent the real material consumption, we have to evaluate material which repetitive purchase in some categories. The most significant number of repetitive material purchase is office chair with 8 po or 23 % of total repetitive po in this category. It mans that office chair has been buy for 8 times in this period (2006-2007). We can see from the figure 5.12 that  the other material have repetitive average consumption. Office chair become the most frequently purchase in this category and should be have an outline agreement. But the consumption trend is a quite odd.  For instance, in one department and one period, user order different brand of office chair in big quantity. And this consumption trend still high in 2007.  Office equipment parts has 4 active OA until 2007. These OA used effectively, and the usage level almost 100% in every period. But the consumption level of office equipment still high, then the recommendation of creating a new Outline Agreement to cover this demand is feasible or increase value and material list. Especially for Office chair which has been bought repeatedly. 

6.5	Analysis of  Effective and efficiency of Outline Agreement
According to table 5.2, we can see active outline agreement which valid until 2007 for 3 material category (Machine and hand tools, Office Equipment/part, Personnel safety Equipment). In generic item data, this material category has the highest consumption level. 
In this observe period, machine and hand tools have 119 number of commitment. It is the biggest number of commitment in generic item analysis in this period. To covered machine and hand tools demand, company already has 2 outline agreement. We can see it in table 6.5 these outline agreement was release in 2006 and the end period is 2008 and 2009. Initial value of these OA is totally about 2,396,182 USD. These OA are used effectively, because the usage level is up to 50% and almost 100% this period. In terms of demand coverage, these OA is not efficient. There are still purchase orders in generic item in this category, which is uncovered demand of these OA.

 
Table 6.1
Outline agreement of machine and handtools


The other material category is Office Equipment parts; this category has 95 number of commitment. This category is low value material but the number of commitment is quite high. Company already have 4 Outline Agreement to cover this category demand. But the reality is consumption level of this category still high, though in this period. Usage level of each OA ( table 6.5) is good, show that these Outline agreement is used  effectively. But for high consumption level in this category, company  have to create a new outline agreement to decrease it or implementing another proposal. New Outline agreement specially for repetitive material purchase in generic item, in this case is office chair. 

 
Table 6.2
Outline agreement of office equipment part
		
Personnel safety equipment consumption levels for this observe period is 105 number of commitment. This category already has 8 Outline Agreement to cover this category demand. But number of commitment that represents consumption level is quite high. This condition shows that Existing Outline agreement in this category is not efficient, not covering optimum number of demand. From the usage level of each existing OA, most of all are not used in effectively. Remained values in the end of period are high; indeed gain to 39.79 % from initial value ( Table 6.7).  So these existing Outlines is not used effectively and not efficient in covering demand. This problem occurs because bad strategy in planning Outline agreement and for long terms period company can lose a lot of money. To avoid this, company have to evaluate the existing OA in this category. So when create a new OA, which related to this category. Stock officer have to considering the consumption trend of material  such as repetitive material purchase. And change planning strategy by extend the OA range period or minimizing the value. 

 
Table 6.3
Outline agreement of personnel safety equipment 

6.6	Analysis of Option proposed in solving Generic item problem.
Generic item considered as a low value purchase, in managing this category TOTAL E&P Indonesie has implemented many systems. Problems that often occurs in Generic item is about high consumption level. This proposals implementation concentrated in different objective. Some of the proposals is concentrated on eliminating or reducing transaction time and cost, the other one is more in finance supervision and control responsibility. 


Method Approaches	Simplify procurement process	Control Request
OA and PA	X	X
e-procurement	X	
Finance supervision		X
p-card thru MoU	X	X

Table 6.4
Option proposed in Solving Generic item problem

•	Outline Agreement and Price Agreement.
Outline agreement and price agreement is one of the solution to manage low value and generic commitment. Creating outline agreement or price agreement coupled with the implementation of auto-CRO will by large be simplifying the procurement process for low value commitment. Anyhow, the prerequisite to establish the OA and PA is that the definition of the item shall be put into SAP. This prerequisite will need big effort from user by the assistance of buyer or stock controller to identify the description, set standardization on product, and set the requirement planning. Nevertheless, coverage of Hand tools, Personnel safety equipment, and office equipment and parts, thru creation of new outline or price agreement is feasible to implement. 

•	e-procurement
Implementation of e-procurement is believed as one way to simplify procurement process. E-procurement has also proofed as the method to reduce acquisition cost and time, in addition if e-proc is coupled by the implementation of the paperless then the acquisition cost and time will significantly decrease. Starting from January 2005, company has implemented full e-procurement process. In managing generic item, the implementation is significant, as shown in the figure below. Starting from 2005 to 2006 number of generic item purchased thru e-procurement is taking off, especially in 2006.

Commitment Value	2005	2006	2007
< 5K	38.7%	89.0%	80.4%

< 20K	46.6%	79.4%	81.6%
< 100K	20.5%	48.0%	87.5%
> 100K	4.5%	15.4%	0.0%

Table 6.5
Implementation of e-proc in yearly basis

The implementation of e-procurement for all generic items is seen as the feasible approach implemented at this moment. In term of the system point of view, e-proc is quite mature, in term of personnel, buyers are familiar with the e-procurement process for two years, and many suppliers are also familiar with this approach.
•	Finance supervision (cost controller)
Finance supervision or cost controller involvement in TI case has been proofed as an efficient approach. 

Dept	% Total Generic Value	Value
DRL/CWO	20.61%	                 4,5 Mio 
FO/MNT	11.73%	                  2,6 Mio
ENG/CST	10.92%	                  2,4 Mio 
SC/STO	9.72%	                  2,1 Mio 
IST/TEL	6.33%	                  1,4 Mio 

Table 6.6
Generic item value in each department
In top 3 departments issuing Purchase Requisition for generic item are having the same trend in term of issuer. In 2005 there are more than 2 people issuing the PR for generic item, in 2006 number of people is decreasing and become 1 person in 2007. 
It seems that user has centralised the creation of PR for generic item, thus more control gain in the first place. In general following the overall trend of generic item, the requests from TOP 3 department are decreasing. Even DRL/CWO has been able to reduce the generic item more than 80% in 2006. For MNT and CST, even though the value was increasing in 2006, but number of commitment generated for generic are decreasing significantly. The data above shows us, that the control given to cost controller has however reduce number of commitment for generic item. A special credit shall be addressed to the effort of cost controller team, this approach shall be continue and even reinforce to ensure the proper request of generic item.
 
Figure 6.2
Evolution of generic commitment value

 
Figure 6.3
Evolution of generic commitment item

•	p-card
P- card is a new proposal for solving generic item problem. So far there is no proper p-card model can be implemented. Meanwhile the utilization of p-card may reduce procurement workload in managing low value and generic item. But not decrese the consumption level of generic item. Even though, Supply chain may find great benefit from the implementation of p-card, but shifting purchasing responsibility to the user, and establishing proper transaction control are two significant concerns that shall be considered. Latest benchmark to other PSC, ConocoPhillips has been working with Bank Niaga to develop the p-card, and they have successfully shifted the procurement responsibility to the user for the transaction less than 500 USD per transaction. The merchants covered only by MoU and span from Pharmacy (Kimia Farma), IT and office equipment (Bhinneka.com), Hand tools (Kawan Lama), and etc.
 
CHAPTER VII
CONCLUSION AND SUGGESTIONS

In this phase, it would be concluded from some analysis produced and give suggestion from the research in TOTAL E&P Indonesie. These conclusions expected to answers some goal of research. 

7.1	Conclusion
According to the research, it can be taken some conclusion:
1.	Main causes of high consumption level of generic item  are uncovered material in outline agreement, human mentality and repetitive material purchase.
2.	Generally, generic item management is improving from the first time implemented. From 2005 to 2007 generic item commitment tend to decrease. This evolution is significant improvement of generic item management.
3.	The highest levels of generic item consumption by “commitment” are in Machine and hand tools category, Personnel safety equipment category, Office Equipment/ parts category.
4.	Active Outline Agreement which related to Machine and hand tools, Personnel safety equipment, and Office Equipment/ parts can not cover the demand of those 3 categories.
5.	There are four option proposed to manage generic item problem; Outline Agreement and Price Agreement, e-procurement, Finance supervision (cost controller) and  p-card

7.2	Suggestions
1.	It is expected to continue the research that hasn’t discussed here and implement the recommendation as result of the research. 
2.	Improving Supply Chain information system to be more user-friendly to the user.
3.	Creating outline agreement has to considering future consumption trend and historical data.
4.	Generic item has to be evaluated periodically.

 
REFERENCE

Chopra.Sunil and Peter Meindl. 2004.”Supply Chain management: Strategy, Planning, and Operation”. New Jersey : Pearson Education.

Pujawan, I Nyoman . 2003. “Supply Chain management”. Surabaya : Guna Widya

Nasution, Arman Hakim.2001. “ Production and Planning Control”. Surabaya : Guna Widya.

Manuhoro, Putranto “Generic item analysis report” Balikpapan.
 
APPENDIX

A.1	Active Outline agreement until 2007
	
Purchasing Document	PO First Release Date	Validity period end
4600000643	18/12/2004	30/09/2007
4600000667	08/12/2004	11/10/2007
4600000673	03/11/2004	01/11/2007
4600000674	01/11/2004	31/03/2008
4600000683	17/11/2004	01/12/2007
4600000686	17/11/2004	31/10/2007
4600000700	13/12/2004	31/12/2007
4600000706	21/12/2004	20/12/2007
4600000707	21/12/2004	20/12/2007
4600000708	21/12/2004	20/12/2007
4600000710	16/12/2004	23/12/2007
4600000725	18/01/2005	02/01/2008
4600000754	27/01/2005	31/12/2007
4600000762	15/02/2005	15/02/2008
4600000768	30/06/2005	16/06/2008
4600000769	07/04/2005	31/12/2007
4600000772	07/04/2005	31/01/2008
4600000800	12/04/2005	07/03/2008
4600000807	16/03/2005	29/11/2007
4600000808	16/05/2005	16/05/2008
4600000810	21/03/2005	18/03/2008
4600000811	22/03/2005	01/04/2008
4600000816	06/04/2005	08/04/2008
4600000827	25/05/2005	06/04/2008
4600000888	12/08/2005	01/08/2007
4600000895	20/07/2005	15/07/2008
4600000896	21/07/2005	22/07/2008
4600000914	19/07/2005	20/07/2008
4600000915	28/07/2005	01/08/2008
4600000935	16/08/2005	11/08/2008
4600000938	12/09/2005	15/09/2008
4600000945	14/09/2005	15/09/2008
4600000946	22/11/2005	01/11/2008
4600000950	31/10/2005	23/08/2008
4600000970	16/11/2005	01/11/2008
4600000971	22/11/2005	01/11/2008
4600000972	07/10/2005	15/10/2008
4600001002	16/03/2006	15/10/2008
4600001004	19/10/2005	27/10/2008
4600001006	28/10/2005	15/11/2008
4600001016	27/10/2005	15/11/2008
4600001028	24/01/2006	31/12/2008
4600001067	27/02/2006	15/05/2008
4600001072	15/03/2006	01/03/2008
4600001076	21/02/2006	10/02/2009
4600001078	24/01/2006	24/01/2008
4600001116	16/03/2006	15/03/2008
4600001125	27/04/2006	01/05/2008
4600001131	29/03/2006	31/03/2008
4600001132	29/03/2006	31/03/2009
4600001145	20/04/2006	15/04/2008
4600001168	13/06/2006	31/05/2009
4600001177	05/06/2006	15/06/2009
4600001178	26/05/2006	31/12/2007
4600001180	26/05/2006	01/06/2009
4600001186	13/06/2006	16/05/2009
4600001194	21/06/2006	01/07/2009
4600001196	02/07/2006	31/12/2008
4600001197	27/06/2006	30/06/2009
4600001205	27/06/2006	12/06/2009
4600001206	20/06/2006	12/06/2009
4600001215	27/07/2006	31/07/2009
4600001219	12/09/2006	31/08/2009
4600001235	31/07/2006	17/07/2007
4600001236	04/08/2006	31/08/2009
4600001237	12/09/2006	31/08/2009
4600001238	31/07/2006	01/08/2008
4600001239	12/09/2006	06/11/2008
4600001245	26/07/2006	29/07/2007
4600001246	26/07/2006	29/07/2008
4600001247	26/07/2006	29/07/2009
4600001248	01/08/2006	20/08/2007
4600001254	08/08/2006	18/06/2008
4600001279	26/09/2006	15/09/2008
4600001282	28/09/2006	14/09/2009
4600001289	11/09/2006	15/09/2008
4600001295	13/10/2006	31/12/2007
4600001299	20/10/2006	31/10/2009
4600001302	27/11/2006	31/12/2008
4600001320	14/11/2006	15/11/2008
4600001330	17/11/2006	15/11/2007
4600001356	23/12/2006	06/10/2007
4600001357	21/12/2006	06/10/2007
4600001375	02/01/2007	31/10/2007
4600001376	02/01/2007	31/12/2007
4600001377	02/01/2007	31/12/2008
4600001386	15/05/2007	03/10/2007
4600001401	10/01/2007	04/08/2007
4600001402	10/01/2007	04/08/2007
4600001416	31/01/2007	01/02/2009
4600001439	06/03/2007	26/02/2009
4600001441	02/04/2007	27/02/2010
4600001442	03/04/2007	31/12/2008
4600001451	08/03/2007	11/11/2007
4600001454	13/03/2007	19/03/2010
4600001455	29/06/2007	30/04/2010
4600001477	16/05/2007	30/03/2009
4600001481	28/05/2007	31/12/2008
4600001482	09/07/2007	10/04/2010
4600001484	04/06/2007	16/04/2010
4600001485	21/06/2007	20/06/2010
4600001503	06/06/2007	10/04/2008
4600001510	25/06/2007	31/12/2008
4600001518	29/06/2007	01/06/2009
4600001545	11/07/2007	26/05/2008
4600001546	11/07/2007	26/05/2008
4600001547	11/07/2007	26/05/2008
4600001573	24/07/2007	01/02/2008
4600001574	24/07/2007	01/02/2008
4600001580	30/07/2007	01/08/2009
4600001583	27/07/2007	24/07/2010